TEA Handbook

Concept

economic

Capex estimation (equipment-first build-up)

Estimating capex means building the plant’s one-time capital up from the ground: cost the dominant equipment per unit operation, sum to a purchased-equipment base, then gross that base up through a stack of factors — installation, off-sites, indirects, contingency, and working capital — to total capex. It is a factored estimate (±30–50%), and because every layer multiplies the one beneath, the equipment base is the number to get right. This page is the method; accounting places the resulting figure in the wider cost ledger that the capital recovery factor annualizes into levelized cost.

Equipment first

The base of the whole estimate is the purchased-equipment cost, built unit operation by unit operation:

  1. Per unit operation, pick the 2–3 items that dominate cost; approximate the rest.
  2. Size each to its design (nameplate) duty — the class-specific measure cost tracks: area for exchangers, power for compressors and pumps, volume for vessels and reactors, plus a design margin (~10–20%).
  3. Scale each from a reference cost with the six-tenths rule, using the class exponent. Past a class’s largest standard unit, capacity is met by numbering upN identical units in parallel, cost ~linear in N (no economy of scale) — rather than one larger item.
  4. Sum to purchased-equipment cost.

Gross up to installed, then roll up to total

  1. Multiply by an installation factor (piping, steel, labor, field indirects; ~2–4 by class, or a single blended Lang factor of ~3.1–4.7 by plant type) for installed cost.

That installed figure is the inside-battery-limits (ISBL) cost — the process plant proper. The roll-up to the figure that actually gets annualized:

Each layer multiplies the one beneath — installation factors the equipment base, indirects factor direct field cost, contingency factors that. The total — not the bare ISBL or purchased-equipment cost — is the defensible “capex,” and what the capital recovery factor carries into levelized cost.

Limits & typical error

See also