TEA Handbook

Concept

Uncertainty & accuracy class (FEL-1/2, ±30%)

cross

Overview

An accuracy class is the ± band a TEA result carries, fixed by how mature and resolved the underlying work is rather than by how clean the arithmetic looks. Early factored estimates — front-end-loading stages FEL-1/2, equivalently AACE Class 5–4 — carry a wide band of order ±30–50%; the class, not the spreadsheet, sets how tight a range and how many significant figures the result can honestly carry.

Body

What it is. Cost-estimating practice ties an estimate’s expected error to its maturity through a small ladder of classes: the more defined the scope, the equipment sizing, and the pricing basis, the tighter the band. The same project is a different accuracy class at different stages of definition, even with identical arithmetic. A seed-stage TEA — a factored, deterministic, proxy-grade model — sits at the wide end of the ladder.

The classes, roughly.

The band propagates and is capped by the weakest input. Precise arithmetic on a ±40% anchor still yields a ±40% result — the output band is set by the worst load-bearing input, not the average, because the calculation cannot manufacture resolution its inputs lack. Capital estimates are also typically asymmetric: overruns are more common than under-runs, so the band often skews high rather than sitting symmetric about the point.

What the class governs. Three downstream quantities all read from this one band: the contingency sized into total plant capital (larger for a less-resolved class); the resolution a headline number may honestly be reported to, since presenting more is false precision; and the credible low/high ranges an input is swept across in a one-way sensitivity. A passing gut-check is itself defined relative to the class — agreement within a factor of ~2 at screening level.

Limits & typical error

See also

Mini-example

Green ammonia’s levelized cost lands at ~$800/t off a factored, proxy-grade build — an FEL-1/2 (Class 5–4) estimate, so its honest band is of order ±30%, roughly $550–1,050/t. The ~$1.0bn total capex behind it carries the same wide class, which is exactly why its contingency line is sized large rather than trimmed. Reporting the result as “$805.27/t” claims a Class-1 resolution that detailed engineering and quotes would be needed to earn — about a hundred times finer than the inputs justify.

Separately, to show the band bounding the level but not the delta: the difference between the gray and green routes, both built on the same shared power and capital anchors, can be resolved more tightly than either absolute ±30% level, because the shared-input error cancels in the gap between them. The accuracy class bounds each absolute number; a controlled difference between two of them can be sharper than the class of either alone.

See also