TEA Handbook

Concept

Discounted cash flow (DCF)

economic

Overview

Discounted cash flow (DCF) values a project by projecting its net cash flow in every year of its life and discounting each back to a present value, summed into a net present value (NPV). It’s the time-resolved alternative to annualizing capital with a capital recovery factor: where the CRF assumes one up-front outlay and flat operation, a DCF carries the actual year-by-year timing of spending, production, and prices.

Body

What it is. Lay out, year by year, the net cash flow CFₜ — revenue − operating cost − capital spend − tax, plus end-of-life salvage — and discount each to the present at the discount rate i (the cost of capital):

NPV = Σ  CFₜ / (1 + i)ᵗ
       t

Positive NPV means the project beats the discount rate; IRR is the i where NPV = 0; payback is when cumulative discounted cash flow turns positive — all outputs of the same projected table.

What it captures that a CRF can’t. Resolving each year separately represents timing a single annualization smears flat: staged capital, a multi-year ramp, changing prices, mid-life replacements, salvage, and tax/depreciation schedules. It can also reflect the financing structure (split and timing of debt and equity).

Relation to the CRF. The CRF is the steady-state special case: for a single up-front capital and flat cash flow, annualizing with CRF and forming a levelized cost ranks projects identically to computing NPVs. The DCF generalizes the same discounting to arbitrary, non-uniform timelines.

What it produces. Questions of value and return over time — NPV, IRR, payback, the effect of phasing — rather than the steady-state cost-per-unit a levelized cost reports. Complementary: levelized cost asks “what does a unit cost to make,” a DCF asks “what is the investment worth, and when.”

Limits & typical error

Mini-example

For the steady green ammonia plant, a DCF adds little. With capital spent essentially up front and output, prices, and costs roughly constant, discounting each year and solving for NPV gives the same per-tonne economics as annualizing total capex with the CRF (the ~$355/t capital share) and adding opex — the flat timeline is exactly what the CRF shortcut is built for.

Edge case: a phased build — electrolyzer capacity added in tranches as offtake grows, output ramping toward nameplate — breaks the flat-timeline assumption, and only a DCF resolves the early, capital-heavy, revenue-light years a single CRF charge spreads uniformly. That’s where the year-by-year detail earns its cost.

See also